Category Archives: Akron

Case Study: Shawnee Path Property Akron, Ohio

Project Type: Preparing the property for sale. The property manager and Realtor recommeded SystemToSell to the out of state owners.

Scope of Work:  Replaced all broken window glass and reglazed windows. Painted the whole interior of the house. Installed new light fixtures. Replaced all the switches, receptacles, and wallplates. Repoured the front concrete steps, Installed new wood handrailings, pressure washed the house, garage, and driveway, refinished the hardwood floors, installed a new floor in kitchen, and remodeled the bathroom.

Timeframe: 25 workdays.

Case Study: Casterton Ave. Apartment Building Akron, Ohio

Scope of Work: SystemToSell was recommended by the Realtor to renovate a 7 unit apartment building in Akron that was just purchased.

Work included:  Electrical, Plumbing, drywall, interior painting, vinyl flooring, new light fixtures, new water heater,  remodeled bathrooms, repaired windows, new roof, mold remediation, and refinished the hardwood floors.

Timeframe: 20 workdays.

Case Study: Merriman Road Property Akron, Ohio

Project Type: Preparing the property for sale. The owners saw SystemToSell working on another property nearby and wanted us to help them get their property in selling condition.

Scope of Work:  Phase One- Exterior. Replaced all broken window glass and reglazed windows, Replaced damaged siding and fascia, Rebuilt concrete steps, Installed new handrailings, pressure washed house, garage, and driveway, and scraped, primed, and painted the house and detached garage.

Phase Two- Interior. Coming this winter.

Timeframe: 28 workdays.

 

 

Case Study: Merriman Road Apartment Building Akron, Ohio

Scope of Work: The Realtor recommended SystemToSell to his client, a Savings & Loan,  to handle the renovation of a bank owned property- a 9 unit apartment building in Akron.

Work included:  Building clean-out. Interior and exterior painting , ceramic tile, plumbing repairs, reglazing tubs and sinks, carpentry, electrical  repairs, new light fixtures, power washing, tree trimming, landscaping, concrete repair, and a gravel driveway.

Timeframe: 35 workdays.

BeforeAfter